Cayo Largo, Cuba -8 MW Heavy Fuel Power Plant (IMG_NUMBER1) Cayo Largo, Cuba -8 MW Heavy Fuel Power Plant (IMG_NUMBER2) Cayo Largo, Cuba -8 MW Heavy Fuel Power Plant (IMG_NUMBER3)

The Cayo Largo power plant was developed in close cooperation with MAN Diesel & Turbo, as part of several projects developed over the late 90’s and early 00’s. The customer was Union Electrica and the plant was designed for based load operation.

Customer: Union Electrica
Application: Base Load
Location: Cayo Largo, Cuba
No. and engine type: 4 x 2 MW 18V 28/32
Plant output: 8 MW
Fuel: HFO
Contract award: May 2005
Construction period: 10 Months
TM’s work scope: Equipment Supply